NEW QUESTION # 36
A project has 16 employees working for four hours per day, 20 employees working six hours per day, and 10 employees working eight hours per day. What is the Full Time Equivalent (FTE) occupancy of the project?

  • A. 0
  • B. 33
  • C. 1
  • D. 2

Answer: A


NEW QUESTION # 37
A new tenant in an existing office building is pursuing LEED certification. The tenant would like to encourage alternative transportation methods. Which of the following items can be used to satisfy this request and achieve LEED Location and Transportation Credit?

  • A. Develop an alternative commuting incentive program
  • B. Provide underground parking
  • C. Designate preferred parking for motorcycles
  • D. Develop on a brownfield site after remediation

Answer: A

Explanation:
An alternative commuting incentive program is a strategy that can be used to encourage alternative transportation methods, such as public transit, carpooling, biking, or walking. An alternative commuting incentive program can provide benefits or rewards for the employees or tenants who use alternative transportation modes, such as subsidies, vouchers, discounts, prizes, recognition, or preferential parking. This strategy can help to achieve LEED Location and Transportation Credit: Alternative Transportation1 . Reference: LEED v4 Green Associate Candidate Handbook1, LEED v4 BD+C Reference Guide


NEW QUESTION # 38
Which of the following concepts uses drought-tolerant native and adaptive plants to promote water conservation?

  • A. Xeriscaplng
  • B. Weather-based irrigation
  • C. Bioswales
  • D. Monoculture

Answer: A

Explanation:
Xeriscaping is a landscaping practice that uses drought-tolerant native and adaptive plants to reduce water use and maintenance. Xeriscaping also incorporates other strategies such as mulching, efficient irrigation, soil improvement, and appropriate design and zoning. By using xeriscaping, projects can conserve water, protect natural habitats, reduce stormwater runoff and pollution, and enhance the aesthetic and ecological value of the site. Reference: LEED v4 Reference Guide for Building Design and Construction, p. 123 1; [Xeriscape Colorado website]


NEW QUESTION # 39
What organization reviews and provides final LEED certification report to projects?

  • A. Green Business Certification Inc.
  • B. U.S. Green Building Council
  • C. ASHRAE
  • D. Green Building Initiative (GBI)

Answer: A

Explanation:
Explanation
The Green Business Certification Inc. (GBCI) reviews and provides the final LEED certification report to projects. GBCI was established in 2008 as a separately incorporated entity with the support of the U.S. Green Building Council (USGBC). GBCI administers project certifications for LEED and other green business certification programs. References: LEED Green Associate Candidate Handbook, U.S. Green Building Council resources


NEW QUESTION # 40
A new tenant in an existing office building is pursuing LEED certification. The tenant would like to encourage alternative transportation methods. Which of the following items can be used to satisfy this request and achieve LEED Location and Transportation Credit?

  • A. Designate preferred parking for motorcycles
  • B. Provide underground parking
  • C. Develop an alternative commuting incentive program
  • D. Develop on a brownfield site after remediation

Answer: A


NEW QUESTION # 41
Which of the following Is a strategy for improving Indoor Environmental Quality during construction?

  • A. Store absorptive-finish materials directly on slab
  • B. Collect construction debris in the mechanical room
  • C. Cover duct work with plastic
  • D. Run permanently installed HVAC with final filtration media

Answer: C

Explanation:
Covering duct work with plastic is a strategy for improving indoor environmental quality during construction. Covering duct work with plastic prevents dust, debris, and contaminants from entering the ducts and affecting the air quality of the building. This also reduces the need for cleaning and maintenance of the ducts after construction. The LEED Green Associate Candidate Handbook states that one of the strategies for achieving indoor environmental quality is to "protect ducts during construction by sealing or covering with plastic" [1, p. 16]. Reference: LEED Green Associate Candidate Handbook, [Indoor Air Quality During Construction | U.S. Environmental Protection Agency]


NEW QUESTION # 42
Which strategy can be used to reduce the amount of construction waste?

  • A. Encourage recycling
  • B. Increase the use of recycled content
  • C. Institute an off-site composting program
  • D. Specify regional materials

Answer: A


NEW QUESTION # 43
The project team is conducting a feasibility study of a building project. The developer has pre-qualified four potential sites that are all financially viable. Within the context of LEED, which site is the most applicable?

  • A. A brownfield site with access to five lines of public transportation and basic services
  • B. A brownfield site in a national park with car access only
  • C. A brownfield site with no access to metro
  • D. A greenfield site with access to public transport and proximity to grocery stores

Answer: A

Explanation:
Explanation
From a LEED perspective, a brownfield site with access to multiple lines of public transportation and basic services would be the most applicable. Brownfield sites are previously developed sites that may be contaminated with hazardous waste or pollution. Developing on these sites can help to clean up and revitalize the area. Access to public transportation reduces the need for private vehicle use, reducing carbon emissions and traffic congestion. References: LEED Green Associate Candidate Handbook, U.S. Green Building Council resources


NEW QUESTION # 44
The LEED Project team performs an initial review that indicates 34 credit points can be achieved from the credit categories. How many additional points would result in the project achieving LEED Silver?

  • A. 30 additional points
  • B. 15 additional points
  • C. 20 additional points
  • D. 10 additional points

Answer: B


NEW QUESTION # 45
Which Is a component of a construction waste management plan?

  • A. Quantity of waste generated from excavated soil
  • B. Distance of the recycling facility from the project site
  • C. Projected cost savings from diverting waste
  • D. List of materials to be diverted from disposal

Answer: D

Explanation:
Explanation
A list of materials to be diverted from disposal is a component of a construction waste management plan. A construction waste management plan is a document that outlines the goals, procedures, and responsibilities for diverting construction and demolition waste from landfills or incinerators. A list of materials to be diverted from disposal identifies the types and quantities of materials that can be recycled, reused, salvaged, or donated, as well as the destinations and methods for diversion. The other options are not components of a construction waste management plan. Projected cost savings from diverting waste is a potential benefit of implementing a construction waste management plan, but it is not a required component. Quantity of waste generated from excavated soil is a factor that affects the construction waste generation rate, but it is not a component of a construction waste management plan. Distance of the recycling facility from the project site is a factor that affects the transportation emissions and costs associated with diverting waste, but it is not acomponent of a construction waste management plan. References: LEED Green Associate Candidate Handbook, page 28; USGBC, [Materials and Resources], page 3.


NEW QUESTION # 46
Which of the following stakeholders are involved in the feedback mechanism?

  • A. Landscape Architect
  • B. Building Energy Modeler
  • C. Occupants
  • D. Civil Engineer

Answer: C

Explanation:
The feedback mechanism is a process of collecting and analyzing data from the building occupants to evaluate the performance of the building and identify opportunities for improvement1. Occupants are the primary source of feedback, as they are the ones who experience the building on a daily basis and can provide valuable insights on its comfort, functionality, and satisfaction2.


NEW QUESTION # 47
Which impact category is weighted the most in the LEED rating systems?

  • A. Water Resources
  • B. Climate Change
  • C. Human Health
  • D. Biodiversity

Answer: B

Explanation:
Climate change is weighted the most in the LEED rating systems because it is considered the most urgent and significant environmental challenge facing humanity. Climate change is caused by the accumulation of greenhouse gases in the atmosphere, which trap heat and alter the global climate patterns. Climate change can have severe consequences for human health, biodiversity, water resources, food security, and social equity. LEED projects can help mitigate climate change by reducing greenhouse gas emissions from building operations and materials, as well as enhancing resilience and adaptation to climate impacts. The LEED impact categories and point allocation process assigns 35% of the total points to climate change. Reference: LEED v4 Impact Category and Point Allocation Process Overview2; LEED v4 BD+C Reference Guide, Introduction, page 9


NEW QUESTION # 48
In the commercial LEED Rating System, which point range will achieve the Certified level of certification?

  • A. 30-39 points
  • B. 40-49 points
  • C. 50-59 points
  • D. 60-69 points

Answer: B

Explanation:
Explanation
LEED certification is awarded based on the number of points a project earns across several categories of green building performance. The range of points required to achieve the Certified level of certification for the commercial LEED Rating System is 40-49, out of a possible 110 points. The other levels of LEED certification are: Silver (50-59 points), Gold (60-79 points), and Platinum (80 or more points)12. References:
LEED v4 Green Associate Candidate Handbook1, LEED v4 BD+C Reference Guide2


NEW QUESTION # 49
Which of the following sites would maximize LEED points under Location and Transportation?

  • A. Infill site on the outskirts of a city with some transportation connectivity
  • B. Greenfield site in an urban area with substantial transit connectivity
  • C. Infill site within an existing neighborhood with substantial transit connectivity
  • D. Greenfield site in a low-density area with some transportation connectivity

Answer: C

Explanation:
An infill site within an existing neighborhood with substantial transit connectivity would maximize LEED points under Location and Transportation. An infill site is a site that has been previously developed or graded and is surrounded by existing development. An existing neighborhood is a geographic area with a variety of land uses, such as residential, commercial, educational, or recreational. Substantial transit connectivity means that the site has access to multiple modes of public transportation, such as buses, trains, light rail, or bicycles. The LEED Green Associate Candidate Handbook states that one of the intents of the Location and Transportation category is to "encourage development within existing communities and public transit infrastructure" [1, p. 12]. Reference: [LEED Green Associate Candidate Handbook], [Location and Transportation | U.S. Green Building Council]


NEW QUESTION # 50
Which industry benchmarking tool is used for measuring ongoing energy performance?

  • A. U.S. Department of Energy's EnerCop
  • B. Bright Power's EnergyScoreCard
  • C. EPA's ENERGY STAR Portfolio Manager
  • D. U.S. Department of Energy's EnergyIQ

Answer: C

Explanation:
Explanation
ENERGY STAR Portfolio Manager is an online tool developed by the U.S. Environmental Protection Agency (EPA) that allows building owners and managers to measure and track the energy and water performance of their buildings, as well as benchmark their buildings against similar buildings nationwide. The tool uses a
1-100 ENERGY STAR score to rate the energy efficiency of a building relative to its peers, where a score of
50 represents median performance and a score of 75 or higher indicates top performance1 . References: LEED v4 Green Associate Candidate Handbook1, ENERGY STAR Portfolio Manager


NEW QUESTION # 51
Which of the following strategies prioritizes cost-effectiveness when designing a LEED project?

  • A. Measuring and verifying systems performance for one year
  • B. Enhanced Commissioning (Cx)
  • C. Applying an integrative design process
  • D. Onsite renewable systems

Answer: C

Explanation:
An integrative design process is a collaborative and holistic approach that involves the project team and stakeholders from the early stages of the project to identify the project goals, analyze the site and climate conditions, explore multiple design options, and optimize the performance and cost-effectiveness of the project. By applying an integrative design process, a LEED project can achieve higher levels of sustainability and efficiency, as well as reduce the risks of errors, delays, and change orders12. Reference: LEED v4 Green Associate Candidate Handbook1, LEED v4 BD+C Reference Guide2


NEW QUESTION # 52
Minimum acoustic performance is a prerequisite requirement that applies to

  • A. LEED for Healthcare
  • B. LEED for Schools
  • C. LEED for Hospitality
  • D. LEED for New Constructions and Major Renovations

Answer: B

Explanation:
Explanation
Minimum acoustic performance is a prerequisite requirement that applies to LEED for Schools projects. The prerequisite aims to provide classrooms that facilitate better teacher-to-student and student-to-student communication through effective acoustic design. The prerequisite requires projects to meet the sound transmission class (STC) ratings for walls, floors, ceilings, doors, and windows; the background noise levels from HVAC systems; and the reverberation time for core learning spaces. By meeting the minimum acoustic performance, projects can improve the indoor environmental quality, enhance the learning outcomes, and reduce thehealth and stress impacts of noise. References: LEED v4 Reference Guide for Building Design and Construction, p. 545 1; [Acoustical Society of America website]


NEW QUESTION # 53
......